What the budgets page shows
The Budgets page breaks down your project's financial position by cost code. For each cost code it shows the budget, what has been ordered, delivered and invoiced, and what is left to spend. It pulls figures from across the project — Variations, Dayworks, Purchase Orders, Delivery Notes, Invoice Checking, Applications, Payment Notices, Invoices and more — and shows them in a single table.
Viewing budgets
- 1
Open a project and click Budgets in the project sidebar.
- 2
Wait for the table to load. The message "We are crunching the numbers... Please wait a moment." appears while the figures are worked out.
How the table is laid out
- Sales and labour rows come first — for example Applications, Certificates, Retentions, MCD / Discount, Sales Invoices, Sales Credit Notes and Labour.
- Your cost codes follow, one row each.
- Total — the bottom row adds up each column.
Click the arrow beside Labour to see its parts, such as Site Labour and Shop Labour.
Budget table columns
The column headings are grouped under Budget Breakdown, Procurement and Sales Breakdown.
| Group | Column | What it shows |
|---|---|---|
| — | Cost Code | The cost code |
| — | Description | The name of the cost code |
| Budget Breakdown | Estimate | The budget imported with your estimate, built from its Buying List |
| Variations | Budget added to the cost code by Variations | |
| Dayworks | Budget added to the cost code by Dayworks | |
| Total Budget | Estimate plus Variations plus Dayworks | |
| Procurement | Ordered | The value ordered against the cost code |
| Delivered | The value delivered against the cost code | |
| Invoiced | The value your suppliers and subcontractors have invoiced | |
| — | Balance | Total Budget minus Invoiced |
| Sales Breakdown | Applications | The value claimed on your Applications |
| Payment Notices | The value certified on Payment Notices | |
| Invoiced | The value of your sales Invoices to the client | |
| Received | Payments recorded as received against your sales Invoices. See Cash Received |
A negative figure, such as an overspent Balance, shows in red with a small down arrow.
There are two Invoiced columns. The one under Procurement is what your suppliers and subcontractors have invoiced you. The one under Sales Breakdown is what you have invoiced your client. Sales figures appear on the sales rows at the top of the table, not on each cost code.
Use the Cost Code filter to narrow the table to one or more cost codes. Each option shows the code and its name.
Quick navigation
Two buttons in the page header provide quick access to related views:
- View Buying List — opens the project's Buying List, with each item's quantities, what is still to order, and costs.
- View Schedule of Rates — opens the schedule of rates tree view.
Next steps
- Schedule of Rates — browse the hierarchical schedule of rates for the project.
- Import Wizard — import cost codes, buying lists, and schedules of rates from Excel.
- The Project Dashboard — return to the project overview with headline cards and charts.
- Variations — raise the Variations that add to a cost code's budget.