What Subcontractor Variations are
A Subcontractor Variation records a change to the scope of a Subcontractor Order — additional work, omitted work, or re-pricing. They work similarly to main contract Variations but are tracked against a specific Subcontractor Order.
Finding Subcontractor Variations
Variations have no link of their own in the sidebar. They sit under their order on the Orders screen.
- 1
Open a project and expand Subcontractors in the sidebar.
- 2
Click Orders.
- 3
Click the arrow next to an order's number to show its Variations.
- 4
Click a Variation's number to open it.
The arrow only appears on orders that have at least one Variation.
Creating a Subcontractor Variation
- 1
On the Subcontractor Orders screen, click New Variation.
- 2
Select the Order. Only
Approvedorders are listed. - 3
Check the Address and Subcontractor. They fill in from the order.
- 4
Set the Variation Date.
- 5
Enter a Description.
- 6
Optionally click Advanced Form to add the Quote Reference, Order Number, start, end and practical completion dates, and notes.
- 7
Click Create. You are taken to the Variation's detail page.
If the order you want is not listed, it is not Approved yet. Approve the order first — see Subcontractor Orders.
If the subcontractor's CIS registration, certificates, cards or insurance policies have expired or expire within 30 days, a warning appears. Click View, read the Warning Details, then click Accept to create the Variation anyway.
Adding items
- 1
On the Variation's detail page, click New Variation Item.
- 2
Enter a Description.
- 3
Set the Date.
- 4
Select a Cost Code.
- 5
Enter the Quantity and Rate, and optionally a Discount % — or switch on Flat Cost and enter a Value £ instead.
- 6
Click Create Item.
You cannot add or change items once the Variation is Approved. The New Variation Item button is greyed out.
Status workflow
| Status | Meaning |
|---|---|
Created | The Variation is being prepared. You can add and change its items. |
Approved | The Variation is accepted and locked. Its items can now be claimed. |
To approve a Variation, click the status button at the top of its detail page and choose Approved. Once it is Approved, the status can no longer be changed from this page, and Modify Variation is no longer shown under Actions.
Choosing Approved again on the order approves all of its Variations at once — see Subcontractor Orders.
Claiming Variation values
A Variation's items only appear on Subcontractor Applications and Subcontractor Invoices once the Variation is Approved. The lines are copied in when the Application or Invoice is created, so approve the Variation before you record the claim.
Next steps
- Subcontractor Orders — raise and approve the orders that Variations change.
- Subcontractor Applications — claim approved Variation values on an Application.
- Subcontractor Invoices — invoice approved Variation values directly.
- Introduction to Subcontractors — see how the subcontractor documents connect.