What Payment Notices are
A Payment Notice (PN) is a formal notification of payment that applies MCD (main contractor's discount) and retention deductions against an approved Application. It records the certificate value, calculates deductions, and tracks remaining amounts.
Viewing Payment Notices
Open a project and click Payment Notices in the sidebar under Contract Management. The table shows all Payment Notices with their number, reference, status, and financial values.
To print a summary of the Payment Notices in the table, click Actions in the page header, then Generate Report, and choose PDF, DOCX or Rich Text Format. The report follows the filters on screen. There is no report option on a single Payment Notice.
Creating a Payment Notice
- 1
Click New Payment Notice in the top-right corner.
- 2
Enter a Reference.
- 3
Check the Applications this notice certifies. Only
ApprovedApplications are listed, and each one shows how much is still left to certify (e.g. APP-00002 — £4,000.00 of £10,000.00). Every Application with value left is ticked for you. - 4
Check the Payment Value — the certificate amount before deductions. It fills in from what the ticked Applications have left. You can lower it, but you cannot certify more than the Applications have left.
- 5
Check the Practical Retention Split %. It starts at the project's retention split, or 50% if the project has none set.
- 6
Check the MCD Value (£) and Retention Value (£) — the amounts to be deducted. Depending on the project's retention method, they fill in from the project's MCD and retention percentages. Change them if needed.
- 7
Optionally set the Payment Received Date.
- 8
Check the Practical Retention Date and Final Retention Date. Both start at the project's dates. If you change the Practical Retention Date, the Final Retention Date moves to one year after it.
- 9
Optionally add Internal Notes. They are not printed on reports.
- 10
Click Create. You are taken to the Payment Notice detail page.
If the retention dates you enter are later than the project's, the project's dates are updated to match.
If the project has no Approved Applications, you see No Approved Applications instead of the form. Click Go to Applications and approve an Application first.
Recording a retention release
When your client releases retention, record it as a Payment Notice with Retention Notice ticked. For the full retention process, see Retention Applications.
- 1
Click New Payment Notice in the top-right corner.
- 2
Enter a Reference.
- 3
Tick Retention Notice at the bottom of the form.
- 4
For the last release, also tick Final Retention Notice. It only appears once Retention Notice is ticked.
- 5
Check the Payment Value. It fills in with the practical retention held back on your ordinary Payment Notices.
- 6
Click Create.
A Retention Notice releases retention rather than certifying Applications, so the Applications, Practical Retention Split %, MCD Value (£) and Retention Value (£) fields are hidden. It is numbered with RET- in front (e.g. RET-PN-00005).
Summary cards
The detail page shows three summary cards at the top:
| Card | Shows | Colour |
|---|---|---|
| Certificate Value | The payment value with remaining amount to apply | Green (positive) |
| MCD Value | The MCD deduction with remaining MCD to apply | Red (negative) |
| Retention Value | The retention deduction with remaining retention to apply. Once values are applied, it also shows the practical value and final value of the retention | Red (negative) |
When a remaining value reaches zero, a badge shows "No Remaining Value", "No Remaining MCD", or "No Remaining Retention".
Auto-applying values
Click Auto Apply Values in the header to share the Payment Notice values across the Applications on this Payment Notice, lowest Application number first. Once applied, the button changes to Values Auto Applied.
If your company certifies manually
Your company can turn on Manual Certify Payment Notices in Settings > Configuration > System Defaults, under Misc. When it is on, you certify each line yourself instead of auto-applying values:
- The New Payment Notice form has no Payment Value, Practical Retention Split %, MCD Value (£) or Retention Value (£) fields.
- On the detail page, type the certified amounts on each line, in the Certified columns — Value, MCD and Retention. You can do this until the Payment Notice is
Submitted. - While you work, the summary cards show Certifying manually.
- When you have finished, click Apply Values. The button then reads Values Applied.
Status workflow
| Status | Meaning |
|---|---|
Pending | Created but not yet submitted |
Submitted | Formally issued. It cannot go back to Pending |
Cancelled | Cancelled |
To submit, click the status button in the header and choose Submitted. If no values have been applied yet, you are asked Submit without applied values? first. Click Submit to go ahead, or Cancel to apply the values first.
Cancelling a Payment Notice
- 1
Click the status button in the header. It shows the current status, for example Pending.
- 2
Choose Cancelled.
Applying to the project
Click Apply to in the header, then choose where the values go:
- Project — apply the values across the project
- Budgets — apply the values to the budgets only
An option shows a tick once its values have been applied.
Other actions
From the Actions dropdown you can:
- Modify Payment Notice — edit the Payment Notice details
- Duplicate Payment Notice — create a copy
- Link with Issue — associate with a project action
Next steps
- Invoices — generate Invoices from Payment Notices.
- Applications — create the payment claims that Payment Notices reference.
- Retention Applications — claim retention back, then record the release as a Retention Notice.
- System Defaults — turn Manual Certify Payment Notices on or off.