What Dayworks are
A Daywork (DW) records work carried out on a time-and-materials basis — outside the main contract scope. Dayworks track the labour, materials, and subcontractor costs involved and can be applied to Applications and budgets.
Viewing Dayworks
Open a project and click Dayworks in the sidebar under Contract Management. Cards above the table total up your Dayworks at each stage: Requested, Priced, Submitted and Overall Total.
The table shows each Daywork's number, name, description, client reference, status, Total Cost and Total Sell. Three Applied To ticks — Budget, Application and Buying List — show where the Daywork has been applied. The last columns show who created it and when.
Filter by Status or Created By.
Creating a Daywork
- 1
Click New Daywork in the top-right corner.
- 2
Enter a Name for the Daywork.
- 3
Optionally enter a Client Reference and Description.
- 4
Optionally add External Notes. These are printed on the report. Notes marked as default in System Notes are filled in for you. Click the notes button in the box to add more.
- 5
Optionally add Internal Notes. These are for your team only and are not printed on reports.
- 6
Click Create. You are taken to the Daywork detail page.
Adding Daywork items
On the detail page, click New Daywork Item to add items to the Daywork. Each item needs a Description, Quantity and Cost Code, and captures costs for materials, labour, and subcontractors.
Markups start from the project's Daywork Markups. To change them for one item, click Advanced Form and edit the Material Markup %, Labour Markup % or Subcon Markup %. Click Add Item to save the item.
The New Daywork Item button is hidden when the Daywork status is Approved. You cannot add items to an approved Daywork.
Status workflow
| Status | Meaning |
|---|---|
Requested | Initial status — the Daywork has been raised |
Priced | Items have been priced |
Submitted | Sent to the client for review |
Approved | Accepted by the client — items and values are locked |
Rejected | The client turned it down. You can resubmit it or cancel it |
Voided | Withdrawn after it was approved |
Cancelled | Cancelled — no further action |
Change the status using the status button in the header. It shows the current status, and its menu only offers the moves allowed from there:
Requested→Priced,SubmittedorCancelledPriced→SubmittedorCancelledSubmitted→Approved,RejectedorCancelledRejected→SubmittedorCancelledApproved→Voidedonly
A Daywork must be Submitted before it can be Approved. Moving to Submitted, Approved, Rejected, Voided or Cancelled needs the matching permission (Submit, Approve, Reject, Void or Cancel).
If you void a Daywork that is already claimed on a Submitted or Approved Application, you are asked to confirm. The window reads This daywork is already claimed. Click Void anyway to go ahead, or Keep it to leave it as it is. Those Applications keep their claim, so you need to deal with them separately.
Applying to the project
Use Apply to in the header to push the Daywork's values into other parts of the project:
- Project — applies to Applications, Budgets, and the Buying List in one go
- Applications only — makes the Daywork available for claiming
- Budgets only — reflects the Daywork in budget totals
- Buying List only — adds items to the procurement buying list
A tick appears next to each option that has already been applied.
Unlike Variations, you can apply a Daywork at any status — it does not have to be approved first. You need the Update Lists permission for Dayworks.
Other actions
From the Actions dropdown you can:
- Generate Report — tick Simplified for the short version, or leave it unticked for the detailed report. Then choose PDF or DOCX.
- Modify Daywork — edit the name, client reference, description, and notes
- Duplicate Daywork — create a copy of the Daywork with the same items
- Link with Issue — attach this Daywork to a project Action. Search by issue number or title. Once linked, the Action's linked-records list shows this Daywork. Each Daywork can be linked to a single Action.
- Add Comment Line — add a heading line that groups items under a section name on the report. Not shown once the Daywork is
Approved. - Cancel Daywork — cancel the Daywork. This is greyed out when the Daywork's status cannot move to
Cancelled(for example, once it isApproved).
Next steps
- Variations — manage contract scope changes.
- Applications — claim Daywork values in payment Applications.
- Budgets — see how applied Dayworks change your budget figures.
- System Notes — set up the default notes that fill in on new Dayworks.