What Direct Costs are
A Direct Cost (DC) records a project expense that is not tied to a Purchase Order — for example, a one-off material purchase, a site service, or an ad hoc expense. You can apply a Direct Cost to your project's budgets, so it shows in the budget figures.
Viewing Direct Costs
Open a project and click Direct Costs in the sidebar under Procurement. The table shows each Direct Cost's number, Status, Description, Order Number, Date and Total Value. The Applied to columns show a tick where it has been applied, and the last columns show who created it and when.
Creating a Direct Cost
- 1
Click New Direct Cost in the top-right corner.
- 2
Enter a Description for the cost.
- 3
Set the Date.
- 4
Optionally change the Order Number. It starts as the project's order number.
- 5
Optionally add Internal Notes. These are not printed on reports.
- 6
Click Create. You are taken to the Direct Cost detail page.
Adding items
From the detail page, you can add items in two ways:
- From the buying list — click Add Item, then Add from Buying List, to select items from the project's buying list. Enter a quantity for each item, then click Add [number] Items (for example, Add 3 Items). Until you enter a quantity, the button reads Select Items.
- Free-type items — click Add Item, then New Direct Cost Item, to add an item that is not on the buying list. Items you type in are also added to the project's Buying List.
If you add more than the buying list has left, a window titled Over the budget quantity lists those lines. Click Continue to add them anyway, or Cancel to go back.
Applying to budgets
- 1
Click Apply to in the header.
- 2
Choose Budgets only. The cost is added to your project's budget figures.
A tick next to Budgets only shows that the Direct Cost has been applied. A faded minus icon shows that it has not.
Confirming a Direct Cost
A new Direct Cost is Draft. When it is right, confirm it.
- 1
Click the status button in the header. It shows Draft.
- 2
Choose Confirmed.
Once a Direct Cost is Confirmed, the Add Item button disappears and you cannot add or change items. To change a Confirmed Direct Cost, use Actions → Revise Direct Cost. This makes a new Draft copy for you to change. The old copy is marked Revised and kept for the record.
Other actions
From the Actions dropdown you can:
- Generate Report — print the Direct Cost. Tick Quantities Only to leave the prices off. Then choose PDF or DOCX.
- Modify Direct Cost — change the Direct Cost's details. Only shown while it is
Draft. - Duplicate Direct Cost — create a copy of the Direct Cost
- Revise Direct Cost — make a new copy to change. Greyed out unless the Direct Cost is
Confirmed. - Add Comment Line — add a heading line that groups items under a section name on the report. Only shown while the Direct Cost is
Draftand has not been applied. - Cancel Direct Cost — cancel the Direct Cost.
- Delete Direct Cost — delete the Direct Cost. You can only delete a Direct Cost that has not been applied.
- Link with Issue — attach this Direct Cost to a project Action. Search by issue number or title. Once linked, the Action's linked-records list shows this Direct Cost. Each Direct Cost can be linked to a single Action.
Next steps
- Purchase Orders — manage formal orders to suppliers.
- Buying List — see the items you can add to a Direct Cost, and how many are still to order.
- Budgets — view how Direct Costs affect the project budget.
- Direct Invoices — record a supplier Invoice that has no Purchase Order behind it.