What Quotes are for
A Quote lets you ask several suppliers to price the same items, then compare their prices side by side. You pick the winning supplier for each line. Project Commander then raises one Purchase Order (PO) for each winning supplier, at the price they quoted.
Quotes is a Beta feature. The Quotes item in the sidebar shows a Beta tag.
Where to find Quotes
Open a project. In the sidebar, under Procurement, click Quotes.
Quotes has its own Quotes module on the RBAC screen. View shows the Quotes item in the sidebar. Create lets you add a quote. Edit covers adding items and suppliers, entering prices, awarding lines and firming. Cancel and Delete cover cancelling and deleting a quote. Raising the Purchase Orders also needs Create under Purchase Orders. If you cannot see Quotes, ask your Super Admin.
The Quotes list
The list shows every quote on the project.
| Column | What it shows |
|---|---|
| # | The quote number, for example QT-00001. Click it to open the quote. |
| Description | What the quote is for. Click it to open the quote. |
| Reference | Your own reference, if you added one. |
| Suppliers | The suppliers asked to price the quote. Shows None yet until you add one. |
| Required By | The date you need the goods by. |
| Awarded | How many lines still need a supplier picked, for example 3 to award. Shows All awarded once every line has a winner, or No lines if the quote is empty. |
| Awarded Value | The total of the winning prices. The Total row at the bottom adds up the column. |
| Status | Pending, Firmed, Ordered or Cancelled. |
| Created By | Who created the quote. |
| Created On | When it was created. |
Filter by Status to narrow the list. A Cancelled quote is shown crossed out.
Statuses
| Status | Meaning |
|---|---|
Pending | The quote is being priced. You can add items and suppliers, enter prices and award lines. |
Firmed | Every line has a winning supplier. Prices, quantities and lines are locked. |
Ordered | The Purchase Orders have been raised from the quote. |
Cancelled | The quote has been cancelled. |
Creating a quote
- 1
Click New Quote in the top-right corner.
- 2
Enter a Description (e.g.
First fix copper). This is the only required field. - 3
Optionally enter a Reference of your own.
- 4
Optionally pick a Required By date. It becomes the delivery date on the Purchase Orders.
- 5
Optionally add Notes. These print on the quote report you send to suppliers.
- 6
Optionally add Internal Notes. These are never printed on reports.
- 7
Click Create Quote.
The new quote opens straight away. Its number and description show at the top of the page. Any Internal Notes show in a box above the price grid.
Notes marked as default under Settings > Configuration > System Notes (the Procurement tab, then Quotes) are filled in for you. You cannot change the description, reference, date or notes once the quote is created.
Adding items and suppliers
Click Add Items to fill the quote. A panel opens with two steps: 1. Items and 2. Suppliers.
Step 1 — choose the items
- 1
Click Add Items.
- 2
Type in Search the buying list... to find a line.
- 3
Type a Quantity against each line you want priced. The grey hint in the box is the quantity still outstanding.
- 4
Click Next: suppliers.
The panel shows each line's Unit, its Outstanding quantity (still to order) and its On Quote quantity (already on quotes that are not cancelled). A line that is already on this quote says Already on this quote.
- Add all fills in the outstanding quantity on every line that is not already on this quote.
- Clear all empties every quantity box.
Adding an item that is not on the buying list
- 1
Type the item's name in Search the buying list....
- 2
Click the button next to the search box.
- 3
If the warning This item may already be on the buying list appears, check the list. Click Add a free-type item anyway only if the item is not there.
- 4
Check the Description.
- 5
Enter the Quantity.
- 6
Click Add item.
A free-type item goes on the quote with the unit Each. It is charged to the SYS000 (Unassigned) cost code, if the project has one.
If the item is already on the buying list, adding it as a free-type item means it gets quoted and ordered twice.
Step 2 — choose the suppliers
- 1
Type in Search suppliers... to find a supplier.
- 2
Tick each supplier you are asking to price the quote.
- 3
Click Add to quote.
Each supplier gets its own price column on the quote. Suppliers come from your company's supplier list. Suppliers already on the quote stay ticked. Click Back to return to the items.
Managing suppliers
Click Manage Suppliers to open the Suppliers on this quote window. The button shows how many suppliers are on the quote. It is available once the quote has lines.
- Quote reference — type the supplier's own quotation number. It is saved when you click away. When the orders are raised, it becomes the Reference on that supplier's Purchase Order. You can still change it after the quote is firmed.
- Add a supplier — invite another supplier. Only while the quote is
Pending. - Bin icon — remove a supplier. Only while the quote is
Pending. Any line they had won goes back to unawarded.
Comparing prices and awarding lines
The quote page is a price grid. Each line is a row. On the left, Unit cost and Total cost (both marked Buying list) show the buying list's net price and that price times the quantity. A free-type line shows a dash here. Each supplier then has a column.
The Totals row at the top shows the buying list total, and for each supplier their Quoted and Awarded totals.
- 1
In a supplier's column, enter the Trade price for the line.
- 2
Enter the Disc % if the supplier gives a discount.
- 3
Click away from the box. The price saves, and the net price each and the Line total are worked out for you.
- 4
Repeat for each supplier and each line.
- 5
On each line, click the tick button in the column of the supplier you are going with.
- The cheapest line total on each row shows in green with the word cheapest.
- If two suppliers quote the same price, both show in amber with Another supplier has quoted the same price on this line.
- A line with no winner shows Not awarded. Click a winning tick again to un-pick it.
- Change a line's Quantity in the grid to re-work every supplier's total on that line.
- Click the bin icon at the end of a row to remove the line.
You can only change prices, quantities and lines while the quote is Pending.
Firming the quote
Firm the quote once every line has a winning supplier.
- 1
Click Firm Quote.
- 2
If Firm with a £0.00 price? appears, check the lines it lists. Click Yes, firm the quote to carry on, or Go back to fix the prices.
- 3
In Raise the purchase orders now?, click Yes, raise the orders or No, just firm it.
If any line still has no supplier picked, the quote is not firmed. The message This quote cannot be firmed yet names the lines still to award.
Once the quote is firmed, Add Items and Firm Quote disappear.
Raising the Purchase Orders
If you chose No, just firm it, click Raise PO's on the quote when you are ready. It does the same as Yes, raise the orders.
Project Commander raises one Purchase Order for each winning supplier. Each order:
- holds the lines that supplier won, at the trade price and discount they quoted
- takes the supplier's quote reference as its Reference
- takes the quote's description, with the order type Material
- is delivered to the project's Address, on the quote's Required By date
- is created as
Pending
You are taken to Purchase Orders. Check each order's delivery details, then firm it. Nothing goes to a supplier until you do. The quote moves to Ordered.
The project must have an Address for the orders to be raised. If it has none, you see a message saying so. Add an address to the project, or raise the orders by hand.
Sending the quote to suppliers
- 1
Click Generate Report.
- 2
Choose PDF or DOCX.
The report lists each line's description, size, unit and quantity, with your Notes. It shows no prices and no supplier names, so you can send the same report to every supplier. Generate Report works once the quote has lines, at any status.
Cancelling or deleting a quote
To cancel a quote, open it and click Cancel Quote. It moves to Cancelled. You cannot cancel a quote while it has Purchase Orders that are not Cancelled. To price the job again, create a new quote.
To delete quotes:
- 1
In the Quotes list, tick the quotes you want to delete.
- 2
Click Delete.
- 3
Confirm the deletion.
Next steps
- Purchase Orders — check and firm the orders raised from a quote.
- Budgets — open the project's buying list, where quote lines come from.
- Suppliers — add the suppliers you ask to price your quotes.
- System Notes — set up default notes for your quotes.